K&K Data Service Inc. · Houston, Texas

Site, foundations, steel and rigging for data centers.

K&K self-performs data center field work from Houston: site and civil work, transformer foundations, steel erection, rigging and equipment setting, and retrofits inside facilities that stay in service. Formed in 2022; the jobs on record run from 2023 through 2025. We are also developing a GB300-class data center project for our own account.

Rui Liang, Founder · inquiry@kkdatasvc.com · +1 234-564-0112

K&K field crew in hard hats erecting galvanized steel framing
K&K crew erecting steel framing at a bitcoin-mining site, 2024–2025.

Field record, 2023–2025

  • Bowie, Texas · 20 MW · 2025Roads, water, transformer foundations, freight and setting; about five months from foundations to handover. Electrical installation by licensed electrical contractors. Punch list closed August 2025.
  • Clinton, Mississippi · 2024 to September 2025Container and transformer foundations, structural steel, grounding grid, transformer setting, fans, fiber, water curtains and fencing. Field team of 11, later 13. Wrap-up and demobilization September 2025.
  • Arkansas · 2024Retrofit inside a facility that stayed in operation: water curtains, negative-pressure fans, hot/cold isolation, water connections and doors. One-year workmanship warranty.
  • West Texas · 2023On a four-site, 120 MW program (planned capacity): site and power development with the utility and county, ground work at two of the four sites, and nearly 100 shipping containers of materials and equipment procured and delivered.

Each job in detail

Work we do with our own crews

Self-performed

  • Site and civil work: grading, drainage, roads, laydown
  • Concrete foundations, including transformer foundations
  • Steel erection for prefabricated building systems
  • Freight, rigging and equipment setting, with our own trucks, trailer and crane
  • Retrofits inside live facilities: cooling, airflow, water

Done by licensed contractors

Licensed electrical contractors install the power. The Engineer of Record named in the project contract seals the design; anything on site that changes the design goes back to that engineer. K&K holds no engineering registration and no electrical contractor license.

Mechanical and refrigeration work that requires a state license is subcontracted.

Each trade in detail

How a K&K site runs

With the utility

  • Load is submitted as separate numbers, not one: billable IT, UPS-protected load, facility demand that the service and generation must carry, and the service ceiling.
  • Energization in agreed steps. A 2025 site came up at about 200 kW for transformer tests, then 1 MW, then 10 MW, scheduled around the grid’s peak windows, with grounding completed to the utility’s specification first.

On the ground

  • A site lead runs work zones, crews, equipment movements and safety coordination every day. Crews live on site in RVs and modular quarters.
  • Hidden work is photographed before cover, with location. The handoff package carries equipment records, installation photos, test results and the open-items list.
  • Records are kept in KK Data Field Logger, the iOS app we built for our own crews.
Finished equipment yard at a bitcoin-mining site where K&K did the field work: rows of prefabricated steel halls, transformers and fenced laydown
Finished yard at a bitcoin-mining site where K&K did the field work.

The finished jobs are bitcoin-mining sites

What carries over to a GPU hall: site and civil work, transformer foundations, power-heavy logistics, utility coordination and work inside live facilities. What does not: an air-cooled mining machine draws about 3–4 kW; a GB300-class rack is about 136 kW and liquid-cooled. Liquid cooling, redundancy and commissioning are in the public drawings for K&K’s own project. That project is not built.

A GB300-class project we are developing

K&K is developing a data center for its own account. The GB300-class project is designed and not yet built. Its reference design is public: four drawing books, 408 pages, free PDF, no account required, with a SHA-256 checksum for every file on the downloads page. GB300 is an NVIDIA product; K&K is not affiliated with NVIDIA.

Electrical drawing book

108 pages · Public Edition P3. 12.47 kV service stepped to 480Y/277 V, 13 UPS paths, a 16-generator plant in four segments, rack and CDU dual-input distribution at 136 kW per rack.

Structural set

187 pages · Public Edition P2. The prefabricated steel building: design basis, member and connection drawings, equipment and support coordination, specifications for rows of liquid-cooled racks.

Network reference design

75 pages · Public Edition P2. GPU hall topology, cabling and interface definitions. In October 2026 an r/HPC reader marked up the first edition and flagged the MPO-12 optical risk and the missing storage paths; P2 adds a storage-access model and optical-channel checks.

Liquid-cooling reference design

38 pages · Public Edition P1. Functional P&ID for 90 racks in five groups: CDU groups, coolant loops, dry and wet cold-source trains. Normal operation evaporates no water.

Download the four books · Data Center Lab: 108 technical articles, two DOI-registered preprints, code on GitHub

Design Development — Public Edition: for study, not construction; no engineer’s seal.

Company facts

Legal name
K&K Data Service Inc.
Office
10750 Hammerly Blvd, Ste 160, Houston, TX 77043
Founded
2022; field work on record since 2023
Phone
+1 234-564-0112
Records
Entity documents, certificates of insurance issued per project, safety program summary and project records: email inquiry@kkdatasvc.com with your organization, the documents you need and the due date. Qualification records

Who answers, and where the crews have worked

What to send

Send the site location, the power status, the equipment list and the date you need a crew. Rui Liang, Founder, reads every brief and replies: whether the scope fits, and a proposed call if it does.